Stepping Up the Base
Walls built on a sloping grade require a stepped base.
- Begin excavation at the lowest point and dig a level trench into the slope until it is deep enough to accommodate the base material and one entire block.
- At this point step up the height of one block, and begin a new section of base trench.
- Continue to step up as needed to top of slope.
- Always bury at least one full unit at each step.
Start retaining wall at the lowest elevation.