Stepping Up the Base

Walls built on a sloping grade require a stepped base.

  • Begin excavation at the lowest point and dig a level trench into the slope until it is deep enough to accommodate the base material and one entire block.
  • At this point step up the height of one block, and begin a new section of base trench.
  • Continue to step up as needed to top of slope.
  • Always bury at least one full unit at each step.
Stepping up the Base Course

Start retaining wall at the lowest elevation.

Stepping up the Base Course